一个虚拟项目团队的成员在不同地点工作。一名团队成员错过其任务完成日期。项目经理发现该团队成员在添加一个其认为客户想要的小功能。 项目经理应该做什么?A virtual project team has members working in different locations.One team has missed their tasks completion date.The project manager discovers that this team member has been adding a small few feature that they believethe client will want.What should the project manager do?()

(A):支持该团队成员的主动思考,并将新功能添加到可交付成果的范围中 Support the team member's proactive thinking,and add the new feature to the deliverable's scope.

(B):要求该团队成员停止新功能的相关工作,并核实可交付成果的范围 Ask the team member to discontinue work on the new feature,and validate thedeliverable's scope.

(C):让团队集中办公,以确保尽快完成任务 Co-locate the team to ensure that the task is completed as soon as possible.

(D):提出一项变更请求,以将新功能包含在范围中 Raise a charge request to include the new feature in the scope.