准备验收文件时,项目经理意识到未能包含两个功能。开发人员表示,虽然这些功能不完整,但客户不会注意到。公司需要为该开发项目开具发票并收取付款,以支付未来六个月的工资。项目经理应该怎么做?While preparing the acceptance document, the project manager realized that two features failed to be include The Developer states that although these features are incomplete, the customers will not notice.The company needs to invoice and receive payments for this project to cover salaries for the next six months.What should a project manager do?()
(A):根据开发人员的意见准备验收文件Prepare the acceptance documents based on the developer’s comment
(B):在准备验收文件之前包含这些功能Include the features prior to preparing the acceptance document
(C):审查需求管理计划Review the requirements management plan
(D):提交变更请求Submit a change requests
查看解析
参考答案
继续答题:下一题