一家公司计划改进其计算机系统,为其用户提供增值功能。项目经理需要从位于全球各地的大量员工那里收集需求,并且需要快速周转。项目经理应该怎么做?A company plans to revamp its computer system to provide value-added features for its clients.The Project managers needs to collect requirements from a large number of staff members located globally,and a quick turnaround is required, What should the project manager do?()
(A):要求所有相关方参与虚拟研讨会Invite all stakeholders to a virtual workshop
(B):与选中的客户一起召开现场研讨会Organize on-site workshop with selected clients
(C):向海外员工分发问卷调查Distribute questionnaires and surveys to overseas staff
(D):确保收集需求符合时间限制Ensure that collecting requirements will meet the time constraints
查看解析
参考答案
继续答题:下一题