一个大型项目正处于收尾阶段,客户拒绝签署同意项目可交付成果,提及之前从未讨论过的需求,项目经理要求与客户开会,以讨论该问题。在会议之前应该查阅下列哪一项?A large project is in its closure phase, The client refuses to sign off on project deliverables, cititing requirements that were not previously discussed, The project manager requests a meeting with the client to discuss the issue.What should be consulted prior to this meeting?()

(A):工作绩效数据 Work performance data

(B):验收标准 Acceptance criteria

(C):经验教训储存库 Lessons learned repository

(D):需求跟踪矩阵 Requirements traceability matrix