项目经理了解到,一名团队成员变更客户需求以提供更高价值,并且实施这一变更的工作已经开始,项目经理应该怎么做?A project manager learns that a learn member changed a customer requirement to provide higher value and that work to implement this change has already starteWhat should the project manager do?()

(A):将该问题上报给项目发起人 Escalate the issue to the project sponsor.

(B):指示该团队成员立即修改工作,满足客户的原始需要 Direct the team member to immediately revise their work to meet the customer’s original requirement.

(C):指示该团队成员停止对变更的工作,直到收到变更控制委员会(CCB)的批准 Instruct the team member to stop working on the change until receipt of change control board(CCB)approval.

(D):批准该变更,并将其记录在变更日志中 Approve the change and document it in the change log.