项目经理已经在一个项目上工作了三个月,该项目是关于在公司的网站上发布了一个新功能,然而,一位关键相关方感到不满,因为可交付成果未能满足他们的期望。 项目经理应该参考什么文件?A project manager has been working for three months on a project to launch a new functionality in a company’s website.However,a key stakeholder is dissatisfied because the deliverable fails to meet their expectations.What document should the project manager consult?()

(A):范围管理计划 Scope management plan

(B):项目范围说明书 Project scope statement

(C):需求跟踪矩阵 Requirements traceability matrix

(D):需求文件 Requirements documentation