项目经理负责管理一个处于执行阶段的项目,并希望审查项目范围以进行成本结算,项目经理发现在工作分解结构(WBS)中遗漏了一项可交付成果。项目经理下一步应该怎么做?A project manager assumes a project during its execution stage and wants to review the project scope for cost settlement.The project manager discovers that some deliverables were missed in the work breakdown structure(WBS).What should the project manager do first?()
(A):询问相关方是否需要添加这些遗漏的可交付成果Ask the stakeholders if these missed deliverables need to be added
(B):请求项目管理办公室(PMO)批准这顼工作的额外资金Request that the project management office(PMO) approve additional funds for this work
(C):根据100%的规则将工作添加到WBS中,并重新计算项目总成本Add the work to the WBS according to the 100 percent rule and recalculate the total project cost
(D):要求主题专家(SMEs)检查这些可交付成果是否有必要Ask subject matter experts(SMEs) to check whether these deliverables are necessary
查看解析
参考答案
继续答题:下一题
更多PMP试题
- 1项目经理得知一次定期项目团队会议上的沟通渠道中断,项目经理应该做什么来确保所有项 目团队成员都同样了解项目情况?
- 2一家工程咨询公司的设计师已完成设计开发并发布设计用于生产,在核实可交付成果过程中发现设计标准发生了变化,已生产的可交付成果不符合新标准。 若要避免这个问题,项目经理应该事先实施哪个规划过程?A designer for an engineering consulting company has completes the design and releases it for production.During the deliverable verification process, it is discovered that the design standard was changed, and that the produced deliverable fails to comply with it.What planning process should the project manager have implemented to avoid this issue?()
- 3在敏捷项目中,产品愿景将会驱动哪一个组件交付:
- 4项目经理有很多年使用预测型方法管理项目的经验,公司为了适应市场的激烈变化,让该项目经理领导 一个使用敏捷方法的项目。在第三个冲刺结束的时候,项目团队仍然没有取得任何实质性的成果,大家感到非常沮丧。 项目经理在接下来的冲刺中应该釆用什么样的领导风格?
- 5一家公司正在采用敏捷方法实施一个软件项目,在冲刺结束后,项目经理提交增量交付物供关键干系人评审,在 冲刺评审会议上,关键干系人反馈,期望的很多特性没有得到满足。但项目团队认为,每一次增量交付物都是按照验 收标准交付的,而且关键相关方也给予了批准。现在项目的SPI是1.43, CPI是1.15。在这种情况下,项目经理应该怎 么做?
- 6公司的年度经营计划表明需要实施一个新的IT系统来改善公司的知识管理,这个系统的基础设施部分 的需求是明确的,但是软件部分的需求还没有更多的细节。项目经理首先应该如何做来管理这个项目?