项目经理与项目相关方和团队成员开会,审查范围管理计划、批准的章程和其他需求文档、专家判断和引导技术用于制定所需产品的详细描述。项目经理还应使用哪一项其他输入?A project manager meets with project stakeholders and team members to review the scope management plan,the approved charter,and other requirements documentation.Expert judgement and facilitation are used to develop a detailed description of the product required.What other input should the project manager use?()

(A):过往项目的经验教训 Lessons learned register from previous projects

(B):假设日志 Assumption log

(C):相关方登记册 Stakeholder register

(D):需求跟踪矩阵 Requirements traceability matrix