项目发起人通知项目经理,即使已完成的项目符合进度计划,在预算范围满足范围需求,但客户对最终产品感到不满意。若要避免这种情况,项目经理应该事先做什么?The project sponsor informs a project manager that even though a completed project was on schedule, within budget, and met scope requirements, the customer is unsatisfied with the final product.What should the project manager have done to avoid this?()

(A):在制定质量管理计划的同时安排更多的会议 Scheduled more meetings while developing a quality management plan.

(B):确保可交付成果符合质量控制测量结果中列出的要求 Ensure that deliverables meet the requirements listed in the quality control measurements.

(C):实施石川图工具 Implement the Ishikawa diagram tool.

(D):完成需求跟踪矩阵 Complete the requirements traceability matrix.

查看解析
参考答案