一家工程咨询公司的设计师已完成设计开发并发布设计用于生产,在核实可交付成果过程中发现设计标准发生了变化,已生产的可交付成果不符合新标准。 若要避免这个问题,项目经理应该事先实施哪个规划过程?A designer for an engineering consulting company has completes the design and releases it for production.During the deliverable verification process, it is discovered that the design standard was changed, and that the produced deliverable fails to comply with it.What planning process should the project manager have implemented to avoid this issue?()

(A):项目整合管理 Project Integration Management

(B):控制质量 Control Quality

(C):规划范围管理 Plan Scope Management

(D):规划质量管理 Plan Quality Management