在项目执行期间,团队识别到几个变更请求,其中包括项目成功所需的功能,这些功能未能包含在需求跟踪矩阵中。 若要避免这种情况,项目经理事先应该做什么?During project execution, the learn identifies several change requests that include functionality needed for project success.These failed to be included the requirements traceability matrix.To avoid this, what should the project manager do beforehand?()

(A):创建工作分解结构(WBS) Created a work breakdown structure (WBS)

(B):定义范围 defined the scope

(C):核实范围 Validated the scope

(D):控制范围 Contro11ed the scope

查看解析
参考答案