一家公司计划扩大其公司网站的服务范围。项目经理开始根据批准的项目章程收集详细的需求。 项目经理应该怎么做才能就项目的可交付成果达成一致意见?A company plans to expand the service scope of its corporate website.The project manager starts to collect detailed requirements based on the approved project charter.What should the project manager do to reach a group consensus on the project’s deliverabies?()
(A):与相关方和主题专家(SMEs)—起召开焦点小组会议Conduct a focus group with stakeholders and subject matter experts(SMEs).
(B):与关键相关方一起使用引导技术Use facilitation skills with key stakeholders.
(C):与相关方一起进行头脑风暴Brainstorm with the stakeholders.
(D):访谈关键相关方和发起人,以获取有关需求的更多信息Interview key stakeholders and sponsors to obtain additional information about requirements.
查看解析
参考答案
继续答题:下一题
更多PMP试题
- 1活动持续时间估算完成后,可以获得:
- 2项目经理正在管理一个先进的计费系统项目。项目经理已经检查了现在的计费系统以及公司项目管理信息系统(PMIS)中的经验教训知识库。项目经理将可能收集更多的系统需求。项目经理下一步应该怎么做?A project manager is leading in a state-of-the art billing system project.The project manager has checked the existing billing system,as well as the lessons learned repository in the company’s project management information system(PMIS).The project manager would like to gather more system requirements.What should the project manager do next?()
- 3完成活动 A 所需的时间经过估算如下:乐观估算时间=8 天;悲观估算时间=38 天;最可能估算时间=20 天;按照三点估算方法进行估算,26 天以后完成的概率大概是:
- 4活动持续时间估算应该由谁来进行?
- 5一家移动互联网公司,釆用敏捷方法实施项目,最近一名团队成员离开了一个重要的软件开发项目,一 名新的团队成员加入。项目团队需要迅速让该成员具备为项目提供绩效的能力。项目经理接下来应该做什么来协助团 队?
- 6项目团队希望聘用第三方公司来设计和执行一部分项目。在选择供应商时,下列哪一项技术能确保公平性?