一个设施改善项目即将完成。客户提供了批准,但注意到一些小缺陷并激活保修程序,客户现在对已移交的设备要求额外批准的范围。项目经理即将开始额外范围的工作。 由于保修程序已生效,项目经理应查阅哪一份计划?A facility improvement project is near completion.The client provided, but noted some minor defects and activated the warranty.The client now requests additional approved scope to equipment that has already been handed over.The project manager is about to start work on the additional scope.Since the warranty is in effect, what plan should the project manager consult?()

(A):质量管理计划 Quality management plan.

(B):变更管理计划 Change management plan.

(C):采购管理计划 Procurement management plan.

(D):需求管理计划 Requirement management plan.