客户在用户测试期间同意最终产品,但现在却有另一种想法。若要解决这个问题,项目经理应该查阅哪一份文件?The client agreed to the final product during user testing, but is now having second thoughts.What should the project manager consult to resolve this issue?()
(A):验收标准Acceptance criteria
(B):质量管理计划Quality management plan
(C):需求文件Requirements documentation
(D):项目章程Project charter