登录  注册

首页->PMP

客户在用户测试期间同意最终产品,但现在却有另一种想法。若要解决这个问题,项目经理应该查阅哪一份文件?The client agreed to the final product during user testing, but is now having second thoughts.What should the project manager consult to resolve this issue?()

(A):验收标准 Acceptance criteria

(B):质量管理计划 Quality management plan

(C):需求文件 Requirements documentation

(D):项目章程 Project charter

查看解析
参考答案
继续答题:下一题