—个专业的项目团队正在管理一个大型项目。上个月,工程顾问提交了最初的设计计划给客户审查,项目经理得知该设计因未能满足客户需求而被拒绝。若要确保更有利的结果,项目经理应该事先做什么?A specialized project team is managing a large project last month engineering consultant submitted the initial design proposal for client review.The project manager learns that the design has been rejected for failing to satisfy customer needs.()

(A):制定项目章程 Developed a project charter

(B):召开项目启动大会 Conducted a kick-off meeting

(C):创建需求跟踪矩阵 Created a requirement traceability matrix

(D):执行相关方分析 Performed a stakeholder analysis

查看解析