项目团队正在努力进行可交付成果的工作,以满足计划的进度。一名团队成员发现范围蔓延正在影响项目成本。项目经理应该怎么做?A project is working hard o deliverables to meet the planned schedule.One team member identifies that scope creep is affecting project costs.What should the project management do?()

(A):执行风险评估和范围变更管理程序 Perform risk assessment and scope change management procedures

(B):允许范围蔓延,并与变更控制委员会(CCB)沟通以获得批准 Estimate the impact on the project and communicate the findings to project stakeholders

(C):估算对项目的影响,并将结果传达给项目相关方 Estimate the impact on the project and communicate the findings to project stakeholders

(D):调查为什么会发生范围蔓延,并立即启动变更管理程序 Investigate why scope creep occurred and immediately initiate change management

查看解析
参考答案